Monday, November 27, 2006

Progress continues along Parker Avenue

The Contractor continues to work on the storm drain system, currently working on the system at the intersection of 4th Street and Parker Avenue. All storm drain lines north of this intersection have been installed. Another storm drain line in front of Safeway has also been installed.

Work continues on forming and pouring sidewalk on the east side of Parker Avenue, with the Contractor currently working on sidewalk between 2nd street and investment. Sidewalk along the east side of Parker/San Pablo curve to 2nd street is completed, along with sidewalk on the west/north side of the curve.


Excavation of the roadway is proceeding between the intersections of California Avenue / San Pablo and First Street / Parker Avenue. The Contractor is also placing and compacting base rock in this section of roadway, with paving of this section schedule for next week, weather permitting.